BlueHost 机房由于动物误闯短路造成变压器爆炸
时间在2小时前,bluehost机房的变压器发生了爆炸事件, 大部分服务器有备用电源,故而未受到影响,但是仍然有少量服务器的备用电源未能正常工作,故而目前处于down机状态,预计30分钟内可以恢复。
最新消息:电力公司已经将变压器修复成功。
Ann A. [8:03:43 PM]: Thank you for contacting the Sales Team. Please give me a moment while I review your question.
Ann A. [8:03:50 PM]: Hi! How can I help you?
FIRST TIME SALES QUESTION [8:07:16 PM]: hello , Is there any news for the bluehost , I got an message II apologize for the problem. Due to a transformer which has exploded, we're currently seeing a power failure, and are working on moving the servers to backup power. We don't currently have an ETA, but are working as quickly as possible to get this back up for you.
[8:07:25 PM]: Is that true?
[8:07:40 PM]: Or just a joke?
Ann A. [8:08:11 PM]: It's true. I just heard from the admin that power has been restored by the power company, and we're now in the process of bringing the servers back online.
[8:08:22 PM]: the sites should be in about 30 minutes.
Ann A. [8:08:51 PM]: It was out for almost 2 hours.
Ann A. [8:09:16 PM]: We thought it was lightening, but found out an animal got stuck in the substation and was electrocuted.
Ann A. [8:09:36 PM]: It's not something that's ever happened here before.
FIRST TIME SALES QUESTION [8:09:37 PM]: OMG
Ann A. [8:10:42 PM]: Just several of the servers were down. We have backup generators that provided power to the majority of our servers, but there was a few that it didn't work for.